CISA Domain 3 - IS Acquisition, Development, and Implementation (12%)¶
Project governance, the development lifecycle, and the controls that must exist before a system goes live. The auditor's angle is whether controls were built in, not bolted on.
Project governance¶
- Business case - the justification: expected benefits, costs, risks, and alternatives. Approved before funding.
- Feasibility study - assesses whether the proposal is achievable technically, economically, operationally, and legally.
- Project sponsor - the business owner accountable for benefits. A project without an engaged sponsor is a standard finding.
- Project steering committee - approves scope, budget, and major changes.
- Critical path - the longest sequence of dependent tasks; it determines the minimum project duration. Slippage on the critical path slips the project.
- Function point analysis - sizing software by delivered functionality rather than lines of code, used for effort estimation.
- Earned value analysis - compares planned versus actual cost and schedule progress.
The auditor's involvement should begin early. Reviewing controls only at go-live is too late to influence design, which is a recurring exam theme.
Development methodologies¶
- Waterfall - sequential phases with formal sign-off between them. Suits stable, well-understood requirements; expensive to change late.
- Agile - iterative delivery in short increments with continuous stakeholder involvement. Suits evolving requirements. Documentation is lighter, which is an audit consideration rather than an excuse for none.
- Prototyping - building a working model to clarify requirements. Risk: the prototype is promoted to production without proper controls.
- RAD (Rapid Application Development) - compressed timelines with heavy user involvement.
- DevOps - development and operations integration with automated pipelines. See CI/CD explained.
- Reverse engineering - deriving design from an existing system, often for replacement.
SDLC phases and the controls in each¶
- Feasibility - business case and alternatives.
- Requirements definition - functional and control requirements. Security and audit requirements belong here, not later.
- Design - architecture, data model, interfaces, and control design.
- Development - coding against standards, with code review and version control.
- Testing - unit, integration, system, and acceptance.
- Implementation - conversion, go-live, and handover.
-
Post-implementation review - did it deliver the expected benefits?
-
User acceptance testing (UAT) - performed by business users against business requirements. Users, not developers, must sign off.
- Regression testing - confirms existing functionality still works after a change.
- Parallel testing - old and new systems run together and results are compared.
- Pilot testing - deployment to a limited group before full rollout.
- Test data - must be representative. Using live production data in test raises a privacy exposure; it should be masked or anonymized.
Implementation and conversion¶
- Direct (big bang) cutover - old system off, new system on. Cheapest, riskiest, no fallback.
- Parallel changeover - both systems run; highest cost, lowest risk, allows result comparison.
- Phased changeover - implemented in stages by module or location.
- Pilot changeover - one site or group first.
- Data conversion controls - record counts, control totals, and reconciliation before and after migration. Conversion is where data integrity is most often lost.
- Fallback / rollback plan - how to return to the previous state. Required before go-live.
- Post-implementation review (PIR) - conducted after the system has stabilized, comparing actual benefits to the business case.
Parallel running is the lowest-risk conversion and direct cutover the highest. Questions about a critical system with no tolerance for failure point to parallel.
Application controls¶
- Input controls - validation, edit checks, range checks, check digits, sequence checks, and batch totals. Preventing bad data entry is cheaper than correcting it later.
- Processing controls - run-to-run totals, reasonableness checks, and reconciliation.
- Output controls - distribution restrictions, reconciliation of totals, and error reporting.
- Check digit - a calculated digit appended to a number to detect transcription errors.
- Hash total - a meaningless-but-verifiable sum used to confirm nothing changed in transit.
- Audit trail - a record of transactions sufficient to reconstruct what happened and who did it.
Change and release management¶
- Change management - request, assess, approve, test, implement, review. Emergency changes still need retrospective approval and documentation.
- Configuration management - controlling and recording versions of code and configuration.
- Version control - the authoritative history of source code.
- Library control - separation of development, test, and production libraries.
- Migration to production - performed by someone independent of the developer. Developers with production migration rights is one of the most common CISA findings.
- Emergency change (firecall) access - temporary elevated access, logged, time-limited, and reviewed afterwards.
Acquisition of third-party systems¶
- Request for proposal (RFP) - documented requirements issued to vendors for comparable bids.
- Vendor evaluation criteria - defined and weighted before proposals arrive, to keep selection objective.
- Escrow agreement - source code held by a third party and released if the vendor fails. The control for vendor viability risk in critical bespoke software.
- Contractual right to audit - retained access to assess the vendor's controls.
- Acceptance criteria - objective tests the delivered system must pass before payment or go-live.
Exam pointers¶
- Security and control requirements must be defined in the requirements phase. Retrofitting is the wrong answer.
- UAT is signed off by users. Developer sign-off is a finding.
- Production data used in testing without masking is a privacy exposure.
- The developer must not migrate their own code to production. Look for segregation of duties.
- Source code escrow addresses vendor failure risk specifically, not quality or support.
- A post-implementation review measures benefits against the business case, not technical success alone.